Stockton Borough Council

Electric vehicle chargers for the North East's first electric bin lorries

In 2021 we worked with Stockton Borough Council, installing 12 three phase EV chargers to support the first electric bin lorries in the North East.

Having assessed that the existing distribution board would not support the new EV charging points and solar panels, we also upgraded the distribution panel and sub distribution. We carried out all design, installation and commissioning so that the council had reassurance of a complete and consistent job and we’ve continued to work with Stockton Council on a number of subsequent projects.

It was a pleasure to work with the council and the Senior Construction Manager there on this innovative initiative and play a part in their carbon reduction plans. We look forward to seeing many other councils following this green initiative and more electric bin lorries on the road!